Snagging records: a checklist that shows what is really outstanding.

Content by DocuSite · Reviewed on 22 October 2026

A mark on a photo doesn't say who should fix it. Keep every snag located, described and ready to check with the team.

The PDF is a site visit record.

What is a snagging record or punch list?

It records issues and unfinished items, often before handover. The point is not to collect marks on photos but to make every item locatable, assignable and verifiable through to closure. In Spain, it is commonly called a lista or acta de repasos.

What to include in a snagging checklist

  • Project, unit or zone, review date and participants.
  • A unique identifier retained across visits.
  • Room and precise location of the affected element.
  • Observable issue description and reference photograph.
  • Agreed owner and deadline, with unconfirmed details made explicit.
  • Status, verification date and closure evidence where checked.

How to organise snags before handover

  1. 1

    Follow a consistent route

    Group by unit, floor or room. Repeat the same route during the verification visit.

  2. 2

    Use one entry per issue

    Do not combine a rubbing window and a paint defect in one task. Each needs an actionable description.

  3. 3

    Agree an owner and deadline

    Record what the team agreed. A default name does not establish that someone accepted the task.

  4. 4

    Separate reported fixes from verified fixes

    Record the completion notice, but close the item after the appropriate check. Link new evidence to the original issue.

Common mistakes

  • Maintaining several unconnected lists and losing the current version.
  • Closing an item solely because someone reported it finished.
  • Treating a snag list as an automatic replacement for formal handover.

Content example

S-012 · Bedroom 2

Check the window leaf closure. Rubbing is observed when operating the handle.

Agreed owner

Joinery team. Deadline to be confirmed.

Status

Awaiting work and subsequent verification on site.

Fictional example. Always check the facts and the requirements applying to your project.

What to check in Spain

For building works covered by Spain's LOE, article 6 regulates reception and reservations. A snag list can describe defects but does not automatically replace the reception record or the record confirming reservations have been remedied. Verify the documents and signatures needed for your handover.

Questions about this document

What is a snagging record?
A record of points needing correction or verification, often before handover. A checklist by zone helps locate each point and follow its resolution.
Can I mark an item as resolved?
The status should reflect what the responsible person verified. A team reporting completion doesn't necessarily mean the fix has been inspected.
Does it replace a formal handover record?
Not necessarily. A snag list documents open items, but handover documents and their effects depend on the contract and applicable framework. Check before using it as a substitute.
How do I avoid losing items between visits?
Keep each item's identifier and update status, evidence and review date. Create a new entry for a different issue instead of overwriting the previous history.

Other project records

Your next visit, with no minutes left to write.

3 free records per company on signup, once only. No card. Android and iPhone app, plus a web version for your computer. Photos and documents sync when connected, with no manual transfers.

Also on your computer, in your web browser.

Select a store to check download availability.